GreenPowerBank Dronten is a battery energy storage system (BESS) and one of three projects within the broader Dronten Energy Storage (Dronter Energie Opslag, DEO) initiative. The three systems are being built side by side in Dronten and are jointly connected to the Closed Distribution System Green (Gesloten Distributiesysteem Groen, GDG) – a private distribution network to which eight wind farms from Windplan Groen and a solar farm in Biddinghuizen are also connected.

MILESTONES

An Overview of Key Stages, Both Completed and Planned

Financial close/NTP (Notice to Proceed)
September 2025

Formal start of the project. The loan is approved by the bank.

Installation of the substation
January 2026

Construction work begins.

Delivery and installation of batteries
June 2026

A crane is deployed to position the batteries.

Start of commissioning and mechanical completion
August 2026

The battery system will be prepared for operation. All connection works will be completed.

Handover/start of integrated testing
November 2026

The batteries will be successfully commissioned and tested.

Commercial Operations Date (COD)
January 2027

Completion of GDG testing. The full system will be handed over to asset management.

Our Contribution

GreenPowerBank Dronten is part of Begro Energy Projects. Ventolines has been closely involved as an integrated service provider since the development phase, supporting Begro on legal and financial matters and managing the project through to construction. We will remain involved after completion, taking on responsibility for asset management.

Impact

In its first phase, GreenPowerBank Dronten will have a storage capacity of 31.6 megawatts. The first-phase installation comprises 27 battery enclosures and is designed to store renewable energy temporarily when there is a surplus of wind or solar generation. During periods of shortfall, the stored energy is fed back into the GDG network, which in turn makes it available to the national grid. In this way, the project makes a meaningful contribution to preventing grid congestion and keeping the electricity network stable. The combined storage capacity across all three large-scale batteries within DEO is 90 megawatts.

Construction of GreenPowerBank Dronten began in September 2025, with a planned Commercial Operations Date (COD) of January 2027 – from which point the battery will be actively contributing to the energy market.

Want to find out more?
Get in touch with
Stefan Hartman

Senior Project Manager

Call +31 6 11 62 99 88 or email stefanhartman@ventolines.nl

Other Projects

Moving forward with renewable energy

Would you like to contribute to the energy transition as part of an ambitious and experienced team?

Join our team!